![]()
PROJECT BASIC DATA
|
COUNTRY: |
ARAB REPUBLIC OF EGYPT |
|
PROJECT TITLE: |
SUEZ GULF/SAMALAUT 500 KV DOUBLE CIRCUIT OVER HEAD TRANSMISSION LINE |
|
EXECUTIVE AGENCY: |
EGYPTIAN ELECTRICITY TRANSMISSION COMPANY (EETC) |
|
PROJECT CONSULTANT: |
ELECTRIC POWER SYSTEMS ENGINEERING COMPANY (EPS) |
|
FINANCING AGENCY: |
INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT (IBRD) & CLEAN TECHNOLOGY FUND (CTF) |
|
LOAN NUMBER: |
79270 |
|
PROJECT ID NUMBER: |
P113416 |
|
LOAN AMOUNT: |
IBRD US$ 70M + CTF US$ 148.25M |
|
BORROWER: |
GOVERNMENT OF EGYPT- MINISTRY OF INTERNATIONAL COOPERATION (MOIC) |
ABBREVIATIONS AND ACRONYMS
|
BOO |
Build Own Operate Clean Technology Fund Egyptian Electricity Holding Company Egyptian Electricity Transmission Company Electric Power Systems Engineering Company Environmental and Social Impact Assessment Feasibility Study Green House Gas International Bank for Reconstruction Development International Competitive Bidding Ministry of Electricity and Energy Over Head Transmission Line Procurement Cycle Project Implementation Unit Prequalification Quality and Cost Based Selection Substation Standard Bidding Documents Transmission Line World Bank |
For the use in this Report "The Project" means the "Suez Gulf/Samalaut 500 kV Double Circuit OHTL"
SUEZ GULF /
SAMALAUT 500 KV
OHTL PROJECT
|
1. Introduction: The Transmission Infrastructure to connect the future Wind Farms at Gulf of Suez and Gabel El-Zait to the Egyptian Unified Power Grid to evacuate over 3000 MW of wind power to the main load centers in Egypt includes the following:
The implementation of the Suez Gulf / Samalaut 500kV OHTL (the Project) is financed through IBRD/CTF loan, while the other three sub-components; construction Suez Gulf (Ras Gharib) substation, Extension of Samalaut substation and construction of 220 kV TL connecting Ras Gharib to Gabal El Zait; are financed through European donors led by European Investment Bank (EIB). 2. Description of Suez Gulf/Samalaut 500 kV OHTL Project: The Suez Gulf/Samalaut 500kV OHTL will be composed of double circuits to connect the Suez Gulf 500kV/220kV GIS Substation to Samalaut 500kV/220kV Conventional substation which lies on the 500 kV backbone system connecting High Dam to Cairo. The objective of constructing the line is to evacuate the electric energy generated from the EG-Wind Development Project to the load centers. The Double Circuit TL when completed will have the capacity to transfer more than 3000 MW of Electric energy. The TL length is about 280 km. The preliminary design for the TL route prepared by the Consultant EPS provided that 89% of the total length of the line will pass through desert land, while the remaining 11% (about 32 km) lies on cultivated lands at Samalaut area. The route for the OHTL was selected with consideration to avoid housing blocks, crossing the Nile River at its narrowest width of 600 m distance and passing far from a mining area. Figures 1 Illustrates the interconnection of Suez Gulf/Samalaut 500 kV OHTL to the Egyptian 500 kV network. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Figures 1: Interconnection of Suez Gulf/Samalaut TL to the 500 kV System |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
3. Log Frame for the Project: The Log Frame for the Suez Gulf/Samalaut 500 kV OHTL is described in Table 1. Table 1: Suez Gulf/Samalaut 500 kV Double Circuit OHTL Project Log Frame
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
4. Organization Management for the Project: The Egyptian Electricity Transmission Company (EETC) is the main executing agency for the project. EETC established a Project Implementation Unit (PIU) and hired the Egyptian Power Systems Engineering Company (EPS) as a consultant for the project. 4.1 Project Implementation Unit (PIU):
EETC established a
Project Implementation Unit (PIU) to manage, co-ordinate, expedite,
supervise, monitor and cost control the project implementation.
4.2 Project Consultant EPS: The Electrical Power Systems Engineering Company (EPS) assigned for the following consultancy services:
4.3 Coordination between PIU and EPS: During implementation, PIU and EPS staff will be responsible for carrying out procurement in accordance with Bank Guidelines. Figure AI.2 Represents the Floxogram for coordination between PIU and EPS. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Figure 2: Fluxogram between PIU (EETC) and the Consultant (EPS) |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
5. Procurement for the Project:
5.1 Procurement Arrangements: Procurement for the Suez Gulf/Samalaut 500 kV OHTL project is carried out in accordance with the World Bank’s "Guidelines: Procurement under IBRD Loans and IDA Credits" dated May 2004 revised October 2006, using the Standard Bidding Documents (SBD) for International Competitive Bidding (ICB) for the Quality and Cost Based Selection (QCBS) Method. The project requires only "Procurement of Works". Works procured under a single responsibility Design, Supply and Installation unit rate based contract for all components (towers, conductors, insulators, ground wires with fiber optics communication links, and foundations) for the complete construction of the Transmission Line based on a basic design given by EETC but having the Contractor full responsibility for the final Design, Supply and Installation of all components. The prequalification and bidding processes are/will be advertised in the Egyptian Newspapers and in the Development Business of United Nations (UNDB), Dg-Market, MOEE and EPS websites. 5.2 Procurement Strategy:
5.3 Procurement Cycle/Time Plan: The Procurement cycle/time Plan has been prepared by the consultant, reviewed and approved by EETC and having the WB no objection as shown in Table 1 and Figure 3. 6. Construction Plan for the Project: Contracting with the Project Contractor is scheduled on 15 December 2011. The Construction of the Suez Gulf/Samalaut 500 kV OHTL Project is planned to start by February 2012 and to be completed by February 2014. 7. Preparation Documents for the Project:
7.1 Feasibility Study: The Feasibility Study for the Project was carried out by EETC and reviewed by EPS that includes technical, economical and environmental aspects. 7.2 Procurement Manual for the Project: Procurement Manual for the Project has been prepared to act as guide along the project’s procurement activities plan. 7.3 Project's Conceptual Design Report: The Project's Preliminary/Conceptual Design Report has been prepared by EPS to provide estimated quantities of tower types, foundations, conductors, etc. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Figure 3: Procurement Cycle Activities |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||